East Halton Wet Grassland Creation

Case study

East Halton Wet Grassland Creation

Wet grassland creation on the banks of the River Humber

ClientAble UK
SectorHabitat conservation and wetlands
Project typeWet grassland creation
Value£355,000
LocationEast Halton
01

Scope

Situated on the banks of the River Humber, the

East Halton wet grassland project took shape

during the course of 2018.

A design involving a network of earth scrapes over

a 44 hectare site with an interlinked framework of drainage ditches and water control structures, this ambitious project sought to provide additional habitat for flora, fauna and wildlife. This project encompassed:

  • Existing live watercourse management
  • Earth bund formations
  • Ditch excavations
  • Earth scrapes to designed plan
  • Inlet reservoir creation
  • Wind turbine installations
  • Culverts
  • Hedgerow removal
  • Footbridge installation
  • Landscaping, planting & seeding
  • Sheet piling Efficiency Part of this project placed importance on adherence to programme and to a certain extent, to expedite it.

To this end, Sweeting Bros Ltd invested in bespoke

designed excavation buckets, to replicate the scrape profile and improve efficiency and timing during the works which spanned a 44 hectare site. Video: https://www.youtube.com/watch? v=wLS7MrCt8QQ Wind turbine pump installation

Bespoke angled bucket to increase efficiency and programme

02

Key Aspects

Water Control Structures & Management

EAST HALTON WET GRASSLAND CREATION A series of water control structures were planned

Client: Able UK as part of the design involving weirs, wind turbine

pumping, valves and pipework to ensure the water Duration: 26 weeks supply was adequately managed and distributed. Value: £355,000 Scope:

Situated on the banks of the River Humber, the

East Halton wet grassland project took shape

during the course of 2018.

A design involving a network of earth scrapes over

a 44 hectare site with an interlinked framework of drainage ditches and water control structures, this ambitious project sought to provide additional habitat for flora, fauna and wildlife. This project encompassed:

  • Existing live watercourse management
  • Earth bund formations
  • Ditch excavations
  • Earth scrapes to designed plan
  • Inlet reservoir creation
  • Wind turbine installations
  • Culverts
  • Hedgerow removal
  • Footbridge installation
  • Landscaping, planting & seeding
  • Sheet piling Efficiency Part of this project placed importance on adherence to programme and to a certain extent, to expedite it.

To this end, Sweeting Bros Ltd invested in bespoke

designed excavation buckets, to replicate the scrape profile and improve efficiency and timing during the works which spanned a 44 hectare site. Video: https://www.youtube.com/watch? v=wLS7MrCt8QQ Wind turbine pump installation

Bespoke angled bucket to increase efficiency and programme

03

Project Images

East Halton Wet Grassland Creation supporting image 4
East Halton Wet Grassland Creation supporting image 5
04

Challenges

using cofferdams, stoplogs and over pumping is often necessary to ensure safe working conditions.

Health & Safety

All workings were carried out compliantly under

CDM 2015 protocols requiring Construction Phase Dust Management

Plans together with comprehensive assessment of In very dry conditions, earth moving can generate all risks and method statements to minimise risks significant dust nuisance to surrounding areas ad it for all work elements. is necessary to deal with this.

Sweeting Bros Ltd are unique in that we have

invested in mountain rescue sleds and equipment to facilitate patient evacuation in the event of an Unexploded Ordnance accident. Our work is often in secluded, When excavating in certain areas, it is necessary to inaccessible areas with very poor ground undertake unexploded ordnance surveys and conditions such that ambulances or a helicopter develop a protocol for dealing with any should any may sink. come to be found.

Nearby Hull was the most heavily bombarded city/

Working with Water town in the UK by the Luftwaffe during World War

II, making almost half the citys’ population Working in or around water poses hazards for homeless and 95% of all homes damaged. employees arising from the natural environment.

Surrounding areas were also heavily bombed,

The presence of vermin and exposure to possibly in error due to decoys with many not found leptospirosis twinned with the possibility of and now lying dormant. drowning, all add to the normal risks involving accidents concerning machinery and moving parts. Sweeting Bros Ltd have significant experience over the last 50 + years of managing this risk.

Pumping out of accumulating / rising ground water

and the management of existing live watercourses

Planning a similar project?